Streets & Sidewalks

To report a blocked sewer or drain: Call MSD at 314-768-6260

Capital Improvements:

2024 – Scope of work is pending. Locations to be published pending final coordination.

2023 – Street repair scope of work included Full Asphalt Reconstruction of the failed sections (see the 2022 Street Assessment) of 7100 Princeton, 7300 Princeton, 7300 Cornell. A small number of sidewalk sections with severe damage (ie, completely ripped out by trees, etc) were contracted for replacement.

2023 – 5 year Capital Improvement Plan (Streets) completed

2022 – Street Assessment updated

U Park retains the engineering firm of Horner & Shifrin for capital improvement planning and technical oversight of projects.